If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

which product is less then 5/8 3/2 x 5/8 9/7 x 5/8 4/3 x 5/8 7/10 x 5/8
I will _______ John if he knows the address.
In the event of the president’s death or resignation, who would be next in line to become president? the vice president the secretary of state the secretary
Why do we use variables, and what is the significance of using them in expressions and equations?
Questions 25,26 28, 29
Round 2722 to the nearest thousand
In which one of the following sentences is the semicolon used correctly? A. Donald has three sisters; Carla, Donna, and Maggie. B. Jacob, who plays in the orche
If you removed the tertiary consumers from a food web, what would be the response of the primary consumers?
which topic or issue would be most appropuate for four-to five-page research paper
how do you write 4 13/20 as a decimal