15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

What’s the inverse of the function? f(x)=3^x+1
Which graph represents the function f(x) = 1/3|x|?​
Ecrivez les droits de l'élève au collège.(a composition of 120 words.)​
answer should be given in m/s​
I WILL GIVE 21 POINTS TO THOSE WHO ANSWER THIS QUESTION RIGHT NOOOO SCAMS AND EXPLAIN WHY THAT IS THE ANSWER
In need of help): please answer ASAP
Through which of the devices listed are we able to connect to wireless networks? Check all that apply. Smart TV Radio Antenna Telephone
In a group of 30 students, the probability that at most 25 of them lime to swim is 45% what is the probability that at least 26 of them like to swim
type a paragraph explaining how the atoms in sugar molecules can be used to form amino acids and other large carbon-based molecules? HELP PLS!!!!!!!!
How do you find the answer for surface area?